Origin Energy Heavy Lift Transfer Operation

Ship to barge March 2012

Qube Energy Bell Bay facility project managed the transfer of 550 ton condensate module from heavy lift vessel to barge. Qube Energy managed the total operation from vessel transfer to load onto barge, ballasting barge and then securing of module on barge for sea transit to Yolla Field.

The transfer operation and securing onto barge was carried out in under 12 hours, barged moved off to Qube Energy other berth so that the expensive HLV could depart saving on expensive demurrage.

The module on barge then sat at Qube Energy facility with various maintenance carried out on module for 3 weeks in readiness for transit to Yolla Field

Total project management and trades supplied by Qube Energy Bell Bay facility